Ulaanbaatar plans to fit electric heating in 7,000 homes in its ger districts this winter to cut air pollution, working with UNICEF, the city said, news site iKon reported on Nov. 19.
The plan covers simple electric heaters for 2,000 households, heaters that store heat for 4,000 and heat pumps for 1,000. The city said it will also build a solar power plant with battery storage for the project.
Ger districts are the neighborhoods of gers, the round felt tents, and small houses around the capital. Many have burned coal for heat. Since 2019, the CHIP program has moved thousands of homes from coal to electric heating, said B. Battor, a UNICEF youth envoy.
The city governor's office and UNICEF opened a three-day fair on Sukhbaatar Square on Nov. 20. It shows residents eight kinds of products, from simple and heat-storage heaters and air-to-air heat pumps to ger insulation kits, along with ventilation devices.
CHIP is a package of ger insulation, heating and ventilation that the Czech aid group People in Need has installed with UNICEF since 2020. More than 6,300 households in 13 provinces and four Ulaanbaatar districts have received it, the group's country representative said.
A full kit costs about 3 million tugrik, said Ch. Zolzaya, a People in Need project officer. Under this winter's plan, residents would pay a third and the city would cover the rest, so a household would pay 1 million to 1.7 million tugrik, depending on the heater. Delivery, installation and the final terms were not yet confirmed, Zolzaya said.
"Our equal development begins in a warm home," said D. Aldardelger, head of the Mongolian Children's Council, at the opening.
Officials also said a feasibility study is done for three small power grids, totaling 2.4 megawatts, to move 800 households in Songinokhairkhan district to electric heating. Projects funded by Switzerland and by an Asian Development Bank grant are moving 750 and 303 households to renewable heating.