Coal for Ulaanbaatar's power plants set to move on a new bypass railway

Trains were due to start carrying coal for the capital's thermal power plants on Nov. 20 along the new Bagakhangai–Khoshigiin Khondii line, which skirts the city center and opened in October.

Thermal Power Plant No. 4, seen across the Tuul River in Ulaanbaatar in July 2023.
Thermal Power Plant No. 4, seen across the Tuul River in Ulaanbaatar in July 2023.Chinneeb, CC BY-SA 4.0, via Wikimedia Commons

Coal for Ulaanbaatar's thermal power plants was due to start moving on Nov. 20 along a new railway that loops around the capital, the daily newspaper Unuudur reported that day.

The line branches off the main railway at Bagakhangai station, runs through Khoshigiin Khondii and Altanbulag soum (district) in Tuv province, and ends at Emeelt, west of the city. It has 177 kilometers of track and opened on Oct. 12.

Minister of Road and Transport Development B. Delgersaikhan announced the Nov. 20 start on Nov. 16. He said the line would ease traffic on the railway through central Ulaanbaatar and let the power plants receive coal without interruption at the winter peak.

The capital's heat and power depend on that coal. In 2025, the Baganuur and Shivee-Ovoo mines sent 6.5 million tonnes of it to Thermal Power Plants No. 2, 3 and 4 and the Amgalan heating plant. Plant No. 4 burned 67 percent of the total.

The new route was built to send freight around Ulaanbaatar rather than through it. At its opening, the news site Nutag reported that the line was expected to carry 20 million tonnes of cargo in its first year and 25 million tonnes later, taking about 1,800 heavy trucks a day off the city's roads.

Since the opening, 34 types of explosive and dangerous cargo may no longer pass through central Ulaanbaatar.

The route also crosses the Tuul River on a 476-meter bridge, the longest in Mongolia.